CONSTRUCTION PROJECT TRACKER
BLO Louisville
Accelerated critical-path schedule · September 1–November 18, 2026
Overall completion0%
Check off completed work to update progress.
Activity
SEP 1SEP 15SEP 29OCT 13OCT 27NOV 10NOV 18
KEY MILESTONES
Opening-day path
SCHEDULE CONTROLS
Protect the finish date
01
Inspection hold points
No backfill, concealment, or ceiling closure until approval.
02
Owner electrician coordination
Make-safe, rough, trim-out, and final must stay on the critical path.
03
Weekend finish work
Paint, LED wall, flooring, and millwork use protected weekend windows.
04
Rolling punch list
Close deficiencies as work proceeds—not at the end.